The Baldwin Library Building Project. The Road From Here. Time Lines From Approval to 2017 Completion.

The Approval Time Line October- December 2013. 
Key dates include tonight's (October 21st) 7:30 Community Forum. Project approval on November 18th by the JLBC. Birmingham City Commission approval on November 25th. Ballot Language Approval by the  Library Board on December 12th and by Birmingham City Commission on December 16th. Voter  approval in the form of a bond issue is expected  in a May 2014 City Election.


Construction Time Line 2014-2017

To enlarge click on time line.